Showing 2601 to 2650 of 32204 written question sets.

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • Why were the Northland Corridor review of 13 February 2025, the Fleetwide Road User Charges review of 31 January 2025, the Ōtaki to North Levin review of 10 April 2025 and the Waitematā Harbour Connections review of 20 February 2026 each…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

I am advised that all of these reviews considered the investment at a business case stage (Gates 1-3), however, given the long-term nature of these investments, these reviews were combined with a Strategic Assessment review (Gate 0). Gate…

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • How many high-risk investment assurance reviews, if any, have been conducted since 1 January 2024 in relation to each of the following NZTA projects: Mt Messenger Bypass, Takitimu North Link, Penlink, Hamilton Southern Links, SH29 Tauriko…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

None of the projects specified in the question have completed Stage Gate Reviews. I am advised Stage Gate Reviews are undertaken at agreed decision points throughout a project's lifecycle and are scheduled in consultation with Treasury.…

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • For how many of the 17 Roads of National Significance has a Risk Profile Assessment been completed, and for how many, if any, has no Risk Profile Assessment yet been undertaken?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

I am advised that Risk Profile Assessments have not been completed for the SH16 NW Alternative Highway, SH6 Hope Bypass and the Hawke’s Bay Expressway.

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • How many NZTA investments currently hold a moderated Risk Profile Assessment rating of high, and how many of those, if any, have not yet had a Gateway review?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

I am advised that of the 30 NZTA investments or activities identified with a Risk Profile Assessment of high, 13 have had Gateway Review processes undertaken. Stage Gate Reviews are undertaken at agreed decision points throughout a…

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What did the November 2025 Targeted Investment Review of the Melling Interchange Project identify as the deficiencies in coordination and decision-making across partner organisations, and which organisations were involved?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

I am advised the issues identified in the November 2025 review were: 1. Cross-partner integration is not at the level required for predictable delivery. 2. Unresolved interfaces present high, immediate schedule and cost exposure. 3.…

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What did the September 2025 Gateway review of Papakura to Drury identify as the respects in which the programme had evolved since the original business case was prepared, and has that business case since been updated?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

The review identified that the Governance Framework had evolved to include Auckland Transport and Iwi which had significant benefit. It also noted that funding pathways and priorities had evolved. The Business Case has since been updated.

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What did the May 2026 Gate 3 review of the Warkworth to Te Hana PPP mean by finding that the procurement process maintained "commercial tension for as long as possible", and at what point in the procurement did the review team consider…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

Gateway reports reflect the opinion of the independent reviewers at the point in time they do the review. I am advised that their finding refers to NZTA’s approach to commercial negotiations on their PPP and their approach to financial…

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What did the April 2025 Gateway review of the Ōtaki to North Levin project record about the state of the project's scope and funding arrangements at the point of investment decision, and what was the project's estimated cost at the time of…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

The review recorded that if the project is to proceed at a cost greater than the approved allocation then additional funding would be required, and that pathways existed to access the funding. It recommended updating the NZTA Board and…

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • Why were a Gate 0 Strategic Assessment review and a Gate 3 Investment Decision review of the Ōtaki to North Levin project conducted as a single combined review on 10 April 2025, rather than sequentially?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

Gateway reviews are undertaken at specific milestones of the investment lifecycle and the type of gate reflects this. Reviews may not always proceed on a sequential basis. I am advised that, in this instance, the project was seeking an…

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What consideration, if any, was given to the findings of the March 2024 and August 2024 assurance reviews of the Te Ahu a Turanga: Manawatū-Tararua Highway Project in the development of the proposal to toll that highway, publicly consulted…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

I am advised that the tolling assessment was carried out independent of the review findings. A copy of the tolling assessment summary is publicly available at: https://nzta.govt.nz/assets/About-us/docs/oia-2024/oia-16810-attachment-1.pdf

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • Was the Minister of Transport advised, at any point between March 2024 and September 2024, that the Te Ahu a Turanga: Manawatū-Tararua Highway Project was subject to an assurance action plan; and if so, on what dates?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

I am advised that officials have not identified any record of the Minister of Transport being advised that Te Ahu a Turanga: Manawatū-Tararua Highway Project was subject to an assurance action plan.

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • Given that the Assurance of Action Plan review of the Te Ahu a Turanga: Manawatū-Tararua Highway Project dated 7 August 2024 is stated to have "increased the project's delivery confidence", what was the project's delivery confidence rating…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

I am advised Amber

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What findings of the Gateway Review Report on the Te Ahu a Turanga: Manawatū-Tararua Highway Project dated 14 March 2024 gave rise to the requirement for an Assurance of Action Plan review of the same project on 7 August 2024?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

I am advised that there was no requirement for an Assurance of Action Plan review. This was initiated by NZTA.

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • How many high-risk investment assurance reviews of the Fleetwide Road User Charges programme have been conducted since 31 January 2025, and if none, at what point is the next such review scheduled?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

No high-risk investment assurance reviews have been conducted since the Gateway Review completed on 31 January 2025. Following that review, the programme scope was reduced to enabling an open Road User Charges (RUC) provider market and…

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What did the January 2025 Gateway review of the Fleetwide Road User Charges programme identify as risks or gaps in relation to funding of the programme, and how much has been appropriated or budgeted to date for delivery of the fleetwide…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

The January 2025 Gateway Review identified uncertainty regarding both immediate and ongoing funding as a key delivery risk. It identified the need for funding through to July 2025 and for ongoing funding thereafter through to programme…

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What "key planning and business case documentation" did the Gateway Review Report on Fleetwide Road User Charges dated 31 January 2025 find required further development, and on what date was each of those documents subsequently completed?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

The Gateway Review identified the draft Indicative Business Case as requiring further development, including further work on risk quantification, modelling and feasibility analysis, cost-benefit analysis, ongoing investment requirements,…

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What did the Gateway Review Report for the National Ticketing Solution, Review 4 Readiness for Service, dated 11 October 2024, conclude about the programme's readiness to commence service, and on what date, if at all, was that report…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

It found the programme is well governed, led and resourced, has stood up the initial Transport, Ticketing and Payments team and is poised for the first delivery of functionality in December 2024, followed by a staged rollout in Canterbury…

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What did the February 2026 Gateway review of the Waitematā Harbour Connections Project identify as the risks to social licence and market confidence for the project, and what action, if any, has been taken in response?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

I am advised the gateway review suggested if engagement is not ramped up in the very short term, there is a risk that mixed messages will continue about the need for the WHC Project, the problems being addressed and the options being…

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • Does the recommendation in the February 2026 Gateway review of the Waitematā Harbour Connections Project regarding contingency beyond conventional P50/P95 analysis indicate that the review team considered the project's cost estimates…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

No. The review recognised that for a project of this scale and duration, contingency above a conventional P50/P95 analysis is required to manage effective management at a strategic and tactical level.

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What did the Gateway Review Report on the Waitematā Harbour Connections Project dated 20 February 2026 mean by recommending "recognition of contingency beyond conventional P50/P95 analysis", and what level of additional contingency, if…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

I am advised that the team did not, nor would it be expected to specify a level of contingency. The Treasury Review was undertaken while work was still being developed and the final Investment Case, supported by the NZTA Board, did…

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • On what date, if at all, was the Gateway Review Report on the Waitematā Harbour Connections Project dated 20 February 2026 provided to the Minister of Transport, and on what date, if at all, was it provided to Cabinet or any Cabinet…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

The Waitematā Harbour Connections Gateway Review Report, dated 20 February 2026, was provided to me by NZTA on 13 March 2026 under the no surprises approach. The report was not provided to Cabinet or any Cabinet committee. Gateway Review…

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What delivery confidence assessment rating, or equivalent overall rating, if any, was assigned by the Investment Review Report on the SH1 Belfast to Pegasus and Woodend Bypass Project, Targeted Investment Review, dated 12 June 2026; and if…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

Green/Amber

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What delivery confidence assessment rating, or equivalent overall rating, if any, was assigned by the Investment Review Report on the SH1 Cambridge to Piarere Project, Targeted Investment Review, dated 22 May 2026; and if none was…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

Green/Amber

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What delivery confidence assessment rating was assigned by the Gateway Review Report on Northland Corridor Section 1: Warkworth to Te Hana PPP, Gate 3 Investment Decision, dated 8 May 2026, expressed on the standard scale of green,…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

Green/Amber

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What delivery confidence assessment rating was assigned by the Gateway Review Report on the Waitematā Harbour Connections Project, Gate 0/2 Strategic Assessment / Delivery Strategy – Detailed Business Case, dated 20 February 2026, noting…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

Amber. Yes.

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What delivery confidence assessment rating, or equivalent overall rating, if any, was assigned by the Investment Review Report on the Melling Interchange Project, Targeted Investment Review, dated 25 November 2025; and if Targeted…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

Amber/Red

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What delivery confidence assessment rating was assigned by the Gateway Review Report on Papakura to Drury, Gate 0 Strategic Assessment Mid-stage Review, dated 17 September 2025, expressed on the standard scale of green, amber/green, amber,…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

Green/Amber

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What delivery confidence assessment rating was assigned by the Gateway Review Report on the NZ Transport Agency Ōtaki to North Levin project, Gate 0 Strategic Assessment / Delivery Strategy and Gate 3 Investment Decision, dated 10 April…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

Amber/Red

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What delivery confidence assessment rating was assigned by the Gateway Review Report on the Te Ahu a Turanga: Manawatū-Tararua Highway Project, Gate 4 Readiness for Service, dated 27 February 2025, expressed on the standard scale of green,…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

Amber

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What delivery confidence assessment rating was assigned by the Gateway Review Report on Te Ara Hauāuru – Northwest Rapid Transit, Gate 2 Delivery Strategy – Detailed Business Case, dated 21 February 2025, expressed on the standard scale of…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

Green/Amber

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What delivery confidence assessment rating was assigned by the Gateway Review Report on the NZ Transport Agency's Northland Corridor Roads of National Significance Project, Gate 0/2 Strategic Assessment / Delivery Strategy – Detailed…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

Green/Amber

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What delivery confidence assessment rating was assigned by the Gateway Review Report on Fleetwide Road User Charges, Gate 0/1 Strategic Assessment / Business Justification and Options, dated 31 January 2025, expressed on the standard scale…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

Amber/Red

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What delivery confidence assessment rating was assigned by the Gateway Review Report for the National Ticketing Solution, Review 4 Readiness for Service, dated 11 October 2024, expressed on the standard scale of green, amber/green, amber,…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

Amber

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What delivery confidence assessment rating was assigned by the Gateway Review Report for the Te Ahu a Turanga: Manawatū-Tararua Highway Project, Assurance of Action Plan, dated 7 August 2024, noting that NZTA has stated the review assessed…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

Green/Amber

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What delivery confidence assessment rating was assigned by the Gateway Review Report for the Te Ahu a Turanga: Manawatū-Tararua Highway Project, Review 0 Mid-Flight Strategic Assessment, dated 14 March 2024, expressed on the standard scale…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

Amber

Question published
Reply lodged

Asked by

Teanau Tuiono

List MP · Green Party

Question

  • With reference to his answer to PWQ 36966 (2026), what information, if any, has the Minister relied upon in expressing confidence that the Chief of Defence Force has fulfilled the requirement in section 45(2)(a) of the Defence Act 1990 to…

Answered by

Hon Paul Goldsmith

List MP · National Party · Minister of Defence

Answer

As noted in the response to question for written answer 36973 (2026), I received advice from the New Zealand Defence Force.

Question published
Reply lodged

Asked by

Teanau Tuiono

List MP · Green Party

Question

  • What advice, reports, briefings, aide memoires, or any other documents has the Minister or any member of their Office requested, if any, during the week beginning 24 August 2026, by title and date?

Answered by

Hon Paul Goldsmith

List MP · National Party · Minister of Defence

Answer

I refer the Member to WPQ 36090 (2026).

Question published
Reply lodged

Asked by

Teanau Tuiono

List MP · Green Party

Question

  • What advice, reports, briefings, aide memoires, or any other documents has the Minister or any member of their Office requested, if any, during the week beginning 24 August 2026, by title and date?

Answered by

Rt Hon Winston Peters

List MP · NZ First · Minister of Foreign Affairs

Answer

The Ministry of Foreign Affairs and Trade publishes a monthly list of titles of advice to Ministers, by the end of the month after the advice is provided. Refer to that list, which can be found here:…

Questions published
Reply lodged

Questions

  • Asked by

    Teanau Tuiono

    List MP · Green Party

    38065

    What advice, reports, briefings, aide memoires, or any other documents has the Minister or any member of their Office requested, if any, during the week beginning 24 August 2026, by title and date?

  • Asked by

    Chris Hipkins

    Member for Remutaka · Labour Party

    38167

    What aides-mémoire, briefings, memos, notes, reports, or any other advice, if any, has the Minister or their Office received during the week beginning 24 August 2026, listed by agency, title and date received?

Answered by

Rt Hon Christopher Luxon

Member for Botany · National Party · Minister for National Security and Intelligence

Answer

As Minister for National Security and Intelligence, I regularly request and receive advice from officials in the Department of the Prime Minister and Cabinet (DPMC) on a range of matters. In accordance with Speaker’s Ruling 210/6, I…

Question published
Reply lodged

Asked by

Teanau Tuiono

List MP · Green Party

Question

  • What advice, reports, briefings, aide memoires, or any other documents has the Minister or any member of their Office requested, if any, during the week beginning 24 August 2026, by title and date?

Answered by

Hon Paul Goldsmith

List MP · National Party · Minister responsible for the GCSB and NZSIS

Answer

I refer the Member to WPQ 36373 (2026).

Questions published
Reply lodged

Questions

  • Asked by

    Teanau Tuiono

    List MP · Green Party

    38067

    What advice, reports, briefings, aide memoires, or any other documents has the Minister or any member of their Office requested, if any, during the week beginning 24 August 2026, by title and date?

  • Asked by

    Rachel Boyack

    Member for Nelson · Labour Party

    38166

    What aides-mémoire, briefings, memos, notes, reports, or any other advice, if any, has the Minister or their Office received during the week beginning 24 August 2026, listed by agency, title and date received?

Answered by

Hon Shane Jones

List MP · NZ First · Minister for Oceans and Fisheries

Answer

Papers with titles currently in the public interest to publish: Scallop Aquaculture in New Zealand (25-Aug-26) Upcoming release of non-fish and protected species capture data for the quarter April to June 2026 (28-Aug-26) In addition to…

Questions published
Reply lodged

Questions

  • Asked by

    Teanau Tuiono

    List MP · Green Party

    38068

    What advice, reports, briefings, aide memoires, or any other documents has the Minister or any member of their Office requested, if any, during the week beginning 24 August 2026, by title and date?

  • Asked by

    Chris Hipkins

    Member for Remutaka · Labour Party

    38161

    What aides-mémoire, briefings, memos, notes, reports, or any other advice, if any, has the Minister or their Office received during the week beginning 24 August 2026, listed by agency, title and date received?

Answered by

Rt Hon Christopher Luxon

Member for Botany · National Party · Prime Minister

Answer

As Prime Minister, I regularly request and receive advice from officials in the Department of the Prime Minister and Cabinet (DPMC) on a range of matters. In accordance with Speaker’s Ruling 210/6, I consider that the time and resources,…

Question published
Reply lodged

Asked by

Teanau Tuiono

List MP · Green Party

Question

  • What advice, reports, briefings, aide memoires, or any other documents has the Minister or any member of their Office requested, if any, during the week beginning 24 August 2026, by title and date?

Answered by

Hon Todd McClay

Member for Rotorua · National Party · Associate Minister of Foreign Affairs

Answer

The titles of advice I have received as Associate Minister of Foreign Affairs are proactively released each month on the Ministry of Foreign Affairs and Trade website at the following link:…

Question published
Reply lodged

Asked by

Teanau Tuiono

List MP · Green Party

Question

  • What advice, reports, briefings, aide memoires, or any other documents has the Minister or any member of their Office requested, if any, during the week beginning 24 August 2026, by title and date?

Answered by

Hon Paul Goldsmith

List MP · National Party · Minister for Space

Answer

I refer the Member to reply number 36375 (2026).

Questions published
Reply lodged

Questions

  • Asked by

    Teanau Tuiono

    List MP · Green Party

    38071

    What advice, reports, briefings, aide memoires, or any other documents has the Minister or any member of their Office requested, if any, during the week beginning 24 August 2026, by title and date?

  • Asked by

    Greg O'Connor

    Member for Ōhāriu · Labour Party

    38130

    What aides-mémoire, briefings, memos, notes, reports, or any other advice, if any, has the Minister or their Office received during the week beginning 24 August 2026, listed by agency, title and date received?

Answered by

Hon Paul Goldsmith

List MP · National Party · Minister for Veterans

Answer

I refer the Member to the attached document.

Question published
Reply lodged

Asked by

Teanau Tuiono

List MP · Green Party

Question

  • What advice, reports, briefings, aide memoires, or any other documents has the Minister or any member of their Office requested, if any, during the week beginning 24 August 2026, by title and date?

Answered by

Hon Brooke van Velden

Member for Tāmaki · ACT Party · Minister for Workplace Relations and Safety

Answer

As the Minister for Workplace Relations and Safety, the titles of advice I requested and received from the Ministry of Business, Innovation and Employment (MBIE) and WorkSafe are considered for proactive release on a regular basis. These…

Question published
Reply lodged

Asked by

Teanau Tuiono

List MP · Green Party

Question

  • What advice, reports, briefings, aide memoires, or any other documents has the Minister or any member of their Office requested, if any, during the week beginning 24 August 2026, by title and date?

Answered by

Hon David Seymour

Member for Epsom · ACT Party · Deputy Prime Minister

Answer

None.

Question published
Reply lodged

Asked by

Teanau Tuiono

List MP · Green Party

Question

  • What advice, reports, briefings, aide memoires, or any other documents has the Minister or any member of their Office requested, if any, during the week beginning 24 August 2026, by title and date?

Answered by

Hon Paul Goldsmith

List MP · National Party · Minister for Pacific Peoples

Answer

I refer the Member to my reply WPQ 16912 (2026).

Questions published
Reply lodged

Questions

  • Asked by

    Teanau Tuiono

    List MP · Green Party

    38075

    What papers, if any, did the Minister take to Cabinet during the week beginning 24 August 2026, by title and date?

  • Asked by

    Chris Hipkins

    Member for Remutaka · Labour Party

    38265

    What papers, if any, did the Minister take to Cabinet during the week beginning 24 August 2026, by title and date?

Answered by

Rt Hon Christopher Luxon

Member for Botany · National Party · Prime Minister

Answer

In my capacity as Prime Minister, I have taken the following paper to Cabinet within the specified timeframe: Proposed Overseas Travel: Prime Minister and Rt Hon Winston Peters - August / September 2026.

Questions published
Reply lodged

Questions

  • Asked by

    Teanau Tuiono

    List MP · Green Party

    38076

    What papers, if any, did the Minister take to Cabinet during the week beginning 24 August 2026, by title and date?

  • Asked by

    Chris Hipkins

    Member for Remutaka · Labour Party

    38271

    What papers, if any, did the Minister take to Cabinet during the week beginning 24 August 2026, by title and date?

Answered by

Rt Hon Christopher Luxon

Member for Botany · National Party · Minister for National Security and Intelligence

Answer

In my capacity as Minister for National Security and Intelligence, I have not presented papers to Cabinet within the specified timeframe.