What delivery confidence assessment rating was assigned by the Gateway Review Report for the Te Ahu a Turanga: Manawatū-Tararua Highway Project, Assurance of Action Plan, dated 7 August 2024, noting that NZTA has stated the review assessed successful delivery as "probable"; and what rating had been assigned by the immediately preceding review of that project?
Answered by
Hon Chris Bishop
Member for Hutt South · National Party · Minister of Transport
Answer
Green/Amber