What delivery confidence assessment rating was assigned by the Gateway Review Report on Northland Corridor Section 1: Warkworth to Te Hana PPP, Gate 3 Investment Decision, dated 8 May 2026, expressed on the standard scale of green, amber/green, amber, amber/red or red; and if no rating was assigned, why not?

Answered Question 38050 (2026)
Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What delivery confidence assessment rating was assigned by the Gateway Review Report on Northland Corridor Section 1: Warkworth to Te Hana PPP, Gate 3 Investment Decision, dated 8 May 2026, expressed on the standard scale of green, amber/green, amber, amber/red or red; and if no rating was assigned, why not?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

Green/Amber