Answered
Question 38045 (2026)
- Question published
- Reply lodged
Bookmark
Asked by
Tangi Utikere
Member for Palmerston North · Labour Party
Question
-
Does the recommendation in the February 2026 Gateway review of the Waitematā Harbour Connections Project regarding contingency beyond conventional P50/P95 analysis indicate that the review team considered the project's cost estimates understated the risk of cost escalation; if not, what did it indicate?
Answered by
Hon Chris Bishop
Member for Hutt South · National Party · Minister of Transport
Answer
No. The review recognised that for a project of this scale and duration, contingency above a conventional P50/P95 analysis is required to manage effective management at a strategic and tactical level.