What did the Gateway Review Report for the National Ticketing Solution, Review 4 Readiness for Service, dated 11 October 2024, conclude about the programme's readiness to commence service, and on what date, if at all, was that report provided to the Minister of Transport?

Answered Question 38043 (2026)
Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What did the Gateway Review Report for the National Ticketing Solution, Review 4 Readiness for Service, dated 11 October 2024, conclude about the programme's readiness to commence service, and on what date, if at all, was that report provided to the Minister of Transport?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

It found the programme is well governed, led and resourced, has stood up the initial Transport, Ticketing and Payments team and is poised for the first delivery of functionality in December 2024, followed by a staged rollout in Canterbury in the first half of 2025. While a copy of the review was not provided, briefings provided in December 2024 and February 2025 included advice on the October 2024 Gateway Review.