- Question published
- Reply lodged
Asked by
Tangi Utikere
Member for Palmerston North · Labour Party
Question
-
How many high-risk investment assurance reviews, if any, have been conducted since 1 January 2024 in relation to each of the following NZTA projects: Mt Messenger Bypass, Takitimu North Link, Penlink, Hamilton Southern Links, SH29 Tauriko and the Second Mt Victoria Tunnel; and where none has been conducted, why not?
Answered by
Hon Chris Bishop
Member for Hutt South · National Party · Minister of Transport
Answer
None of the projects specified in the question have completed Stage Gate Reviews. I am advised Stage Gate Reviews are undertaken at agreed decision points throughout a project's lifecycle and are scheduled in consultation with Treasury. These projects have not yet reached the relevant project milestone or decision point that would trigger a Stage Gate Review.