Showing 51 to 100 of 363 written question sets.

Question published
Reply lodged

Asked by

Rachel Brooking

Member for Dunedin · Labour Party

Question

  • (matches this search)

    How many, if any, grocery or supermarket projects does he expect to be lodged for referral under the Fast-track Approvals Act this year?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

Seeking a referral under the Fast-track Approvals Act 2024 (the Act) is a commercial decision for prospective applicants. As such, I am not party to any potential applications under the Act.

Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • (matches this search)

    What advice, if any, did the New Zealand Infrastructure Commission give the Government in 2025 on whether an increase in fuel excise duty is required to fund the Roads of National Significance programme?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

The New Zealand Infrastructure Commission did not provide me with advice on the relationship between fuel excise duty revenue and the Government’s ability to meet its Roads of National Significance programme.

Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • (matches this search)

    What aides-mémoire, briefings, memos, notes, reports, or any other advice, if any, has the Minister or their Office received during the week beginning 6 July 2026, listed by agency, title and date received?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

I receive advice from a range of agencies. I am advised that the Treasury and the New Zealand Infrastructure Commission regularly publish monthly lists of titles of advice to Ministers. I refer the member to those lists, which can be found…

Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • (matches this search)

    What papers, if any, did the Minister take to Cabinet during the week beginning 6 July 2026, by title and date?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

None.

Question published
Reply lodged

Asked by

Francisco Hernandez

List MP · Green Party

Question

  • (matches this search)

    How much, if any, have the Minister’s departments, agencies, crown entities and any other bodies that the Minister is responsible for, if any, budgeted for the carbon neutral government programme in the 2026/27 financial year?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

For the Treasury, I refer the Member to the answer to Written Question 31072 (2026). For my other agencies: None.

Question published
Reply lodged

Asked by

Francisco Hernandez

List MP · Green Party

Question

  • (matches this search)

    How much in total, if any, was spent on renumeration of Crown appointees in the Minister's departments, crown entities and any other bodies that the Minister is responsible for, if any, for the 2022-2023 financial year?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

For the Treasury, I refer the Member to the answer to Written Question 31074 (2026). For my other agencies: National Infrastructure Funding and Financing Limited: None. Crown Infrastructure Delivery (CID): I refer the Member to CID's…

Question published
Reply lodged

Asked by

Francisco Hernandez

List MP · Green Party

Question

  • (matches this search)

    How much in total, if any, was spent on renumeration of Crown appointees in the Minister's departments, crown entities and any other bodies that the Minister is responsible for, if any, for the 2023-24 financial year?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

For the Treasury, I refer the Member to the answer to Written Question 31081 (2026). For my other agencies: National Infrastructure Funding and Financing Limited: None. Crown Infrastructure Delivery (CID): I refer the Member to CID's…

Question published
Reply lodged

Asked by

Francisco Hernandez

List MP · Green Party

Question

  • (matches this search)

    How much in total, if any, is forecast to be spent on renumeration of Crown appointees in the Minister's departments, crown entities and any other bodies that the Minister is responsible for, if any, for the 2026-27 financial year?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

For the Treasury, I refer the Member to the answer to Written Question 31084 (2026). For my other agencies: National Infrastructure Funding and Financing Limited: $581,614.00 Crown Infrastructure Delivery: $325,000.00 Infrastructure…

Question published
Reply lodged

Asked by

Francisco Hernandez

List MP · Green Party

Question

  • (matches this search)

    How much in total, if any, was spent on renumeration of Crown appointees in the Minister's departments, crown entities and any other bodies that the Minister is responsible for, if any, for the 2025-26 financial year?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

For the Treasury, I refer the Member to the answer to Written Question 31085 (2026). For my other agencies: National Infrastructure Funding and Financing Limited: $475,520.00 Crown Infrastructure Delivery: $370,000.00 Infrastructure…

Question published
Reply lodged

Asked by

Francisco Hernandez

List MP · Green Party

Question

  • (matches this search)

    How much, if any, did the Minister’s departments, agencies, crown entities and any other bodies that the Minister is responsible for, if any, spend on the carbon neutral government programme in the 2025/26 financial year?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

For the Treasury, I refer the Member to the answer to Written Question 31102 (2026). For my other agencies: None.

Question published
Reply lodged

Asked by

Barbara Edmonds

Member for Mana · Labour Party

Question

  • (matches this search)

    Has the Minister instructed any chief executive not to action the head count reduction targets or baseline savings exercise as part of Budget 2026, and if so, which chief executives?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

I refer the member to page 72 of the Budget 2026 - Summary of Initiatives - 28 May 2026 which outlines information relevant to the Baseline Savings initiative including which agencies are excluded.…

Question published
Reply lodged

Asked by

Barbara Edmonds

Member for Mana · Labour Party

Question

  • (matches this search)

    What instructions, if any, has the Minister given to the Chief Executives they are responsible about the public service headcount reduction targets or baseline savings exercise as part of Budget 2026?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

I refer the member to the reply to written question 30814 by the Minister of Finance.

Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • (matches this search)

    What aides-mémoire, briefings, memos, notes, reports, or any other advice, if any, has the Minister or their Office received during the week beginning 29 June 2026, listed by agency, title and date received?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

I receive advice from a range of agencies. I am advised that the Treasury and the New Zealand Infrastructure Commission regularly publish monthly lists of titles of advice to Ministers. I refer the member to those lists, which can be found…

Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • (matches this search)

    What papers, if any, did the Minister take to Cabinet during the week beginning 29 June 2026, by title and date?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

None.

Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • (matches this search)

    What aides-mémoire, briefings, memos, notes, reports, or any other advice, if any, has the Minister or their Office received during the week beginning 22 June 2026, listed by agency, title and date received?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

I receive advice from a range of agencies. I am advised that the Treasury and the New Zealand Infrastructure Commission regularly publish monthly lists of titles of advice to Ministers. I refer the member to those lists, which can be found…

Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • (matches this search)

    What papers, if any, did the Minister take to Cabinet during the week beginning 22 June 2026, by title and date?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

New Zealand Infrastructure Commission: Appointment - 22 June Fast-track Approvals (Buller Plateaux Continuation and Other Projects) Order 2026 - 22 June

Question published
Reply lodged

Asked by

Dan Rosewarne

List MP · Labour Party

Question

  • (matches this search)

    What correspondence, including emails and letters, if any, has he received from Hon Matt Doocey regarding the Pegasus Golf Course for the month beginning 22 May 2026?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

Hon Matt Doocey shared a Facebook post about the project with me via text in May.

Question published
Reply lodged

Asked by

Dan Rosewarne

List MP · Labour Party

Question

  • (matches this search)

    What correspondence, including emails and letters, if any, has he received from Hon Matt Doocey regarding the Pegasus Golf Course for the month beginning 8 May 2026?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

Hon Matt Doocey shared a Facebook post about the project with me via text in May.

Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • (matches this search)

    Further to reply 24306 (2026), how much Infrastructure Reference Group funding, if any, was returned to the Crown as a result of the reduced scope of the Tara-Ika Growth Area project?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

IRG funding to be returned to Crown late 2026 as a result of reduced scope: $1.95 million.

Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • (matches this search)

    Further to reply 24306 (2026), what was the original agreed scope and Infrastructure Reference Group funding, and what is the reduced scope and reduced funding, for the Tara-Ika Growth Area project?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

Reduced scope/funding from IRG relates to: - The Stormwater Local Reserves project is now to be delivered by Horowhenua District Council (HDC) once a solution has been identified (IRG loan funding of $1.75 million); and - The North South…

Question published
Reply lodged

Asked by

Ginny Andersen

List MP · Labour Party

Question

  • (matches this search)

    What communications, if any, have occurred between him and Minister Stanford, or her office, about the Ministry of Education’s proposed Regional Supplier Programme for school property?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

None.

Question published
Reply lodged

Asked by

Ginny Andersen

List MP · Labour Party

Question

  • (matches this search)

    Has he seen any advice on the Ministry of Education’s proposed Regional Supplier Programme for school property; if so, what did that advice say about how the Ministry of Education’s proposal would impact suppliers?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

No.

Question published
Reply lodged

Asked by

Ginny Andersen

List MP · Labour Party

Question

  • (matches this search)

    Has he seen any advice on the Ministry of Education’s proposed Regional Supplier Programme for school property; if so, what did that advice say about how the Ministry of Education’s proposal would affect construction jobs?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

No.

Question published
Reply lodged

Asked by

Ginny Andersen

List MP · Labour Party

Question

  • (matches this search)

    What advice, if any, has he seen on the Ministry of Education’s proposed Regional Supplier Programme for school property?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

None.

Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • (matches this search)

    Further to reply 24306 (2026), what is the revised expected completion date for the new Whanganui Hub, and which facilities included in the original scope will no longer be delivered?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

The original scope of the new Whanganui Hub included a new Police Hub Building and a Custodial Care Facility. The revised scope for the IRG-funded portion includes only the Custodial Facility and has a revised completion date of June 2027.…

Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • (matches this search)

    Further to reply 24306 (2026), what was the original budget and the current estimated cost of the new Whanganui Hub, and has any funding been returned to the Crown?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

The original budget for the new Whanganui Hub and Custodial Facility was $25 million. The current estimated cost of the Custodial Facility is $25 million with the estimated cost of the new Whanganui Hub to be confirmed once the design is…

Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • (matches this search)

    Further to reply 24306 (2026), what was the original agreed scope and what is the reduced scope of the new Whanganui Hub for New Zealand Police?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

The original scope of the new Whanganui Hub agreed under the IRG “Shovel Ready” programme included construction of a NZ Police hub building and a custodial care facility. Only the custodial facility will now be delivered under the IRG…

Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • (matches this search)

    Further to reply 24306 (2026), of the total Crown funding committed to the Te Whau Pathway, how much has been spent and how much, if any, has been returned to the Crown?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

Crown funding spent to 23 June 2026: $36.87 million. $0 Crown funding has been returned to Crown.

Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • (matches this search)

    Further to reply 24306 (2026), how many kilometres of the originally agreed Te Whau Pathway will not be delivered under the reduced scope, and does the Government intend to fund the remaining sections?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

Approximately 2.4km of pathway ~700m of pathway will not be delivered under the reduced scope. The Government currently does not intend to fund the remaining sections under the IRG Shovel ready programme

Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • (matches this search)

    Further to reply 24306 (2026), which infrastructure works originally agreed for the Tara-Ika Growth Area will not be delivered under the reduced scope?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

The full scope will be delivered over time by Horowhenua District Council but outside of the IRG Shovel ready programme to fit in with another wider programme.

Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • (matches this search)

    Further to reply 24306 (2026), what was the original agreed scope, including the length of pathway, and what is the reduced scope now to be delivered for the Te Whau Pathway?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

Original scope – Construction of approx. 4km of 4m wide boardwalk and 1km of concrete path to contribute towards the 15km long shared pathway. Reduced Scope to be delivered - Construction of approx. 1.6km of 4m wide boardwalk and 270m of…

Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • (matches this search)

    Further to reply 24306 (2026), what is the current expected completion date for the Northwestern Busway, and has it changed from the original funding agreement?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

Current expected completion date: October 2026 Original funding agreement completion date: March 2024

Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • (matches this search)

    Further to reply 24306 (2026), has the total cost of, or Crown funding for, the Northwestern Busway changed as a result of the contract split?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

I am advised the contract split is not considered to have increased the total cost of the IRG funded components of the Northwestern Busway. Rather, significant increases in land acquisition and project cost escalation pressures increased…

Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • (matches this search)

    Further to reply 24306 (2026), why was delivery of the Northwestern Busway split from one delivery agent to two, being Auckland Transport and the NZ Transport Agency?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

New Zealand Transport Agency (NZTA) and Auckland Transport (AT) are jointly delivering the Northwestern Busway programme. The transfer of some responsibilities from AT to NZTA for the Westgate Station and Brigham Creek land components of…

Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • (matches this search)

    What aides-mémoire, briefings, memos, notes, reports, or any other advice, if any, has the Minister or their Office received during the week beginning 15 June 2026, listed by agency, title and date received?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

I receive advice from a range of agencies. I am advised that the Treasury and the New Zealand Infrastructure Commission regularly publish monthly lists of titles of advice to Ministers. I refer the member to those lists, which can be found…

Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • (matches this search)

    What papers, if any, did the Minister take to Cabinet during the week beginning 15 June 2026, by title and date?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

Government Response to the National Infrastructure Plan - 15 June 2026

Questions published
See individual question dates
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Questions

  • 28204 (matches this search)

    Question published

    Further to the reply to question 20908 (2026), does the statement that the information "is not available" mean that the Crown records no costs incurred on business cases, design, and preparatory work for these projects, or that such costs…

  • 28205 (matches this search)

    Question published

    Further to the reply to question 20908 (2026), what total costs has the Crown incurred to date on business cases, design, and other preparatory work for each project that was presented as a potential Public-Private Partnership opportunity…

  • 28726 (matches this search)

    Question published

    Further to the reply to question 20908 (2026), what costs has the Crown incurred to date on business cases, design, and other preparatory work for the proposed new Waitakere and Rotorua courthouses, promoted as a Public-Private Partnership…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

The Crown records costs incurred on business cases, design, and preparatory work for these projects, but such costs are unlikely to be able to be disaggregated by the procurement model. Budget funding towards the delivery of the Rotorua…

Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • (matches this search)

    What aides-mémoire, briefings, memos, notes, reports, or any other advice, if any, has the Minister or their Office received during the week beginning 8 June 2026, listed by agency, title and date received?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

I receive advice from a range of agencies. I am advised that the Treasury and the New Zealand Infrastructure Commission regularly publish monthly lists of titles of advice to Ministers. I refer the member to those lists, which can be found…

Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • (matches this search)

    What papers, if any, did the Minister take to Cabinet during the week beginning 8 June 2026, by title and date?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

None.

Questions published
Reply lodged

Asked by

Debbie Ngarewa-Packer

Member for Te Tai Hauāuru · Te Pāti Māori

Questions

  • 28699 (matches this search)

    What specific measures, if any, are in place to monitor or mitigate perceived preferential access arising from political donations associated with Fast-track applicants?

  • 28713 (matches this search)

    What assessments, if any, have been undertaken on whether political donations from fast‑track applicants, applicant representatives, directors, shareholders, consultants, lobbyists, or associated entities could create a perception of…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

Donations to an individual Minister’s election campaign are considered and managed in accordance with the Cabinet Manual guidance on pecuniary interests. Donations to political parties are not generally treated as resulting in a pecuniary…

Question published
Reply lodged

Asked by

Debbie Ngarewa-Packer

Member for Te Tai Hauāuru · Te Pāti Māori

Question

  • (matches this search)

    How many Fast-track applicants, applicant representatives, directors, shareholders, consultants, lobbyists, or associated entities, if any, attended meetings, events, briefings, receptions, or engagements with Ministers prior to submitting…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

My Ministerial diary is proactively released on the Beehive website every month. I invite the Member to access it here:…

Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • (matches this search)

    Further to the reply to question 20908 (2026), which projects presented as potential Public-Private Partnership opportunities at the Government's March 2025 Investment Summit are no longer being procured as Public-Private Partnerships?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

Justice courthouses were presented as potential PPP opportunities at the March Investment Summit. A standard procurement approach, rather than PPP procurement, will be now be used. I refer the Member to the answer to Written Question 20911…

Question published
Reply lodged

Asked by

Camilla Belich

List MP · Labour Party

Question

  • (matches this search)

    In how many cases, if any, was a director or member of a board or committee excluded from or absent for more than one-third of agenda items during their tenure at any agency, department, Crown entity, company, or other organisation for…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

I do not hold this information. This information is held by the individual entities.

Question published
Reply lodged

Asked by

Camilla Belich

List MP · Labour Party

Question

  • (matches this search)

    What total fees or other remuneration, if any, were paid to each director or member of a board or committee subject to a conflict of interest management plan at any agency, department, Crown entity, company, or other organisation for which…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

I do not hold this information. Entities are responsible for managing all payments related to board and committee fees and expenses, and for the ongoing management of conflict management plans in accordance with their own Board policies…

Question published
Reply lodged

Asked by

Camilla Belich

List MP · Labour Party

Question

  • (matches this search)

    What total fees or other remuneration, if any, were paid to each director or member of a board or committee subject to a conflict of interest management plan at any agency, department, Crown entity, company, or other organisation for which…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

I do not hold this information. Entities are responsible for managing all payments related to board and committee fees and expenses, and for the ongoing management of conflict management plans in accordance with their own Board policies…

Question published
Reply lodged

Asked by

Camilla Belich

List MP · Labour Party

Question

  • (matches this search)

    How many agenda items, if any, was each director or member of any board, committee, or other body of any agency, department, Crown entity, company, or other organisation for which the Minister is responsible excluded from or absent for…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

I do not hold this information. This information is held by the individual entities from which the member is welcome to seek this information directly. Conflicts of interest are managed under standard conflict management plans established…

Question published
Reply lodged

Asked by

Camilla Belich

List MP · Labour Party

Question

  • (matches this search)

    How many people, if any, appointed or reappointed by the Minister since 27 November 2023 to any board, committee, or other body of any agency, department, Crown entity, company, or other organisation for which the Minister is responsible…

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

I am not aware of any appointments or reappointments I have made since 27 November 2023 where a conflict of interest management plan was put in place prior to the appointment. It is the responsibility of each Board to ensure all conflict…

Question published
Reply lodged

Asked by

Teanau Tuiono

List MP · Green Party

Question

  • (matches this search)

    What advice, reports, briefings, emails, aide memoires, or any other documents has the Minister or any member of their Office seen, if any, about WorkSafe New Zealand safety requirements for fuel storage tanks?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

I am advised that the Treasury publishes on its website a list of the reports and briefings that it has provided to Ministers. I refer the member to that list, which can be found here:…

Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • (matches this search)

    What aides-mémoire, briefings, memos, notes, reports, or any other advice, if any, has the Minister or their Office received during the week beginning 1 June 2026, listed by agency, title and date received?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

I receive advice from a range of agencies. I am advised that the Treasury and the New Zealand Infrastructure Commission regularly publish monthly lists of titles of advice to Ministers. I refer the member to those lists, which can be found…

Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • (matches this search)

    What papers, if any, did the Minister take to Cabinet during the week beginning 1 June 2026, by title and date?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

None.