Skip to main content

Further to reply 24306 (2026), how much Infrastructure Reference Group funding, if any, was returned to the Crown as a result of the reduced scope of the Tara-Ika Growth Area project?

Answered Question 29580 (2026)
Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • Further to reply 24306 (2026), how much Infrastructure Reference Group funding, if any, was returned to the Crown as a result of the reduced scope of the Tara-Ika Growth Area project?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

IRG funding to be returned to Crown late 2026 as a result of reduced scope: $1.95 million.