Question 29148 (2026)
- Question published
- Reply lodged
Bookmark
Asked by
Kieran McAnulty
List MP · Labour Party
Question
-
Further to reply 24306 (2026), what was the original agreed scope, including the length of pathway, and what is the reduced scope now to be delivered for the Te Whau Pathway?
Answered by
Hon Chris Bishop
Member for Hutt South · National Party · Minister for Infrastructure
Answer
Original scope – Construction of approx. 4km of 4m wide boardwalk and 1km of concrete path to contribute towards the 15km long shared pathway. Reduced Scope to be delivered - Construction of approx. 1.6km of 4m wide boardwalk and 270m of concrete path Roberts Field to SH16 plus section Wingate Street to Ken Maunder Park to contribute towards the 15km long shared pathway (Area 1 and Area 2).