- Question published
- Reply lodged
Asked by
Kieran McAnulty
List MP · Labour Party
Question
-
Further to reply 24306 (2026), what is the revised expected completion date for the new Whanganui Hub, and which facilities included in the original scope will no longer be delivered?
Answered by
Hon Chris Bishop
Member for Hutt South · National Party · Minister for Infrastructure
Answer
The original scope of the new Whanganui Hub included a new Police Hub Building and a Custodial Care Facility. The revised scope for the IRG-funded portion includes only the Custodial Facility and has a revised completion date of June 2027. New funding for the Whanganui Police Hub Building was announced in Budget 2026 and this portion of the project will be delivered outside of the IRG “Shovel Ready” programme. It is due for opening in early 2029 and the final budget is currently being worked on.