Answered
Question 29144 (2026)
- Question published
- Reply lodged
Bookmark
Asked by
Kieran McAnulty
List MP · Labour Party
Question
-
Further to reply 24306 (2026), what was the original agreed scope and what is the reduced scope of the new Whanganui Hub for New Zealand Police?
Answered by
Hon Chris Bishop
Member for Hutt South · National Party · Minister for Infrastructure
Answer
The original scope of the new Whanganui Hub agreed under the IRG “Shovel Ready” programme included construction of a NZ Police hub building and a custodial care facility. Only the custodial facility will now be delivered under the IRG “Shovel Ready” programme with the NZ Police hub building to be delivered with funding announced in Budget 2026.