Further to Reply 34450 (2026), has the bid cost reimbursement for the two unsuccessful Warkworth to Te Hana bidders now been finalised; if so, what amount was paid to each and on what date, and if not, when is finalisation expected?

Answered Question 39700 (2026)
Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • Further to Reply 34450 (2026), has the bid cost reimbursement for the two unsuccessful Warkworth to Te Hana bidders now been finalised; if so, what amount was paid to each and on what date, and if not, when is finalisation expected?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

No. I am advised that NZ Transport Agency Waka Kotahi (NZTA) expects to reimburse the two unsuccessful respondents in October 2026.