Question 34450 (2026)
- Question published
- Reply lodged
Bookmark
Asked by
Tangi Utikere
Member for Palmerston North · Labour Party
Question
-
How much, if any, was paid in bid cost reimbursement in relation to Warkworth to Te Hana, and what amount was paid to each of the three shortlisted consortia?
Answered by
Hon Chris Bishop
Member for Hutt South · National Party · Minister of Transport
Answer
The Northland Corridor Stage 1, Warkworth to Te Hana Public Private Partnership project has a budgeted bid stipend of $80m to reimburse up to 80% of costs for the two unsuccessful bidders (capped at $40m per bidder). Work to finalise the reimbursement for the two unsuccessful bidders is ongoing.