Answered
Question 38632 (2026)
- Question published
- Reply lodged
Bookmark
Asked by
Kieran McAnulty
List MP · Labour Party
Question
-
Further to his reply to Question 33993 (2026), how many, if any, of the 299 houses that Kāinga Ora recorded as delivered in 2025/26 that had not been issued a Code of Compliance Certificate (CCC) on or before 30 June 2026 received a CCC by 31 August 2026?
Answered by
Hon Chris Bishop
Member for Hutt South · National Party · Minister of Housing
Answer
I am advised by Kāinga Ora that 41 of these homes received their CCC by 31 August 2026. A CCC is not required for occupation of Kāinga Ora homes on Kāinga Ora-owned land. In some cases, homes are occupied while CCC documentation is being processed, and the timing of CCC issuance varies between Building Consent Authorities and regions