How much has NZTA spent to date on the development and procurement of the Warkworth to Te Hana project, broken down by internal costs and external legal, financial, technical and probity advisers, if any?

Answered Question 34451 (2026)
Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • How much has NZTA spent to date on the development and procurement of the Warkworth to Te Hana project, broken down by internal costs and external legal, financial, technical and probity advisers, if any?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

NZTA has spent a total of $98 million on external professional services costs associated with the development and procurement of the Warkworth to Te Hana project. This includes: - $27.7 million in legal services and advice - $7 million in financial services - $42.8 in technical services (primarily geotechnical investigations) - $0.5m in probity services and advice.