What measures, if any, have been implemented to ensure that companies previously declined consents by the courts or the EPA - including Trans-Tasman Resources Ltd - are not using the $80 million fund as a back-door pathway to re-enter the approvals process?

Answered Question 9028 (2026)
Question published
Reply lodged

Asked by

Debbie Ngarewa-Packer

Member for Te Tai Hauāuru · Te Pāti Māori

Question

  • What measures, if any, have been implemented to ensure that companies previously declined consents by the courts or the EPA - including Trans-Tasman Resources Ltd - are not using the $80 million fund as a back-door pathway to re-enter the approvals process?

Answered by

Hon Shane Jones

List MP · NZ First · Minister for Regional Development

Answer

The Regional Infrastructure Fund (RIF) application process does not affect decisions of the courts or the Environmental Protection Authority. All RIF projects must demonstrate a credible pathway to obtaining required consents.