How many projects have been declined approval under the Fast-Track Approvals Act 2024 between its gazetting and 17 March 2026?

Answered Question 8836 (2026)
Question published
Reply lodged

Asked by

Lan Pham

List MP · Green Party

Question

  • How many projects have been declined approval under the Fast-Track Approvals Act 2024 between its gazetting and 17 March 2026?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister for Infrastructure

Answer

As of 17 March 2026, no substantive applications have been declined. Noting that this does not include the Delmore, or Taranaki VTM Project. The respective applicant for each project decided to withdraw their application from consideration by an expert panel, after having received a draft decline decision.