Skip to main content

What is the total or estimated cost of all work by NZTA on the State Highway 2 (SH2) Waioweka Gorge closure, up to now, since the severe weather and multiple large slips on Friday, 16 January 2026?

Answered Question 7413 (2026)
Question published
Reply lodged

Asked by

Jo Luxton

List MP · Labour Party

Question

  • What is the total or estimated cost of all work by NZTA on the State Highway 2 (SH2) Waioweka Gorge closure, up to now, since the severe weather and multiple large slips on Friday, 16 January 2026?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

NZTA advises me that the total spend to February 28 is $3,804,863.10