Further to WQ answer 57472, what were the disbenefits calculated for the SH1 Improvements Project for vehicle operating costs and emissions, in dollars?

Answered Question 709 (2026)
Question published
Reply lodged

Asked by

Julie Anne Genter

Member for Rongotai · Green Party

Question

  • Further to WQ answer 57472, what were the disbenefits calculated for the SH1 Improvements Project for vehicle operating costs and emissions, in dollars?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

The State Highway 1 Wellington improvements project has total economic benefits estimated at between $1.6 billion and $2.9 billion Net Present Value (NPV) over 60 years. Disbenefits for vehicle operating costs are $82 million NPV, and $33 million NPV for emissions.