Question
-
What is the earliest and latest timeframes the LNG terminal could be operational?
Answered by
Hon Simon Watts
Member for North Shore · National Party · Minister for Energy
Answer
This will be subject to the specific contractual arrangement, I have indicated the terminal could be operational as early as 2027 or early 2028