What advice or information, if any, did the Minister rely on to arrive at the "north of a billion dollars" figure for an LNG import terminal?

Answered Question 5981 (2026)
Question published
Reply lodged

Asked by

Scott Willis

List MP · Green Party

Question

  • What advice or information, if any, did the Minister rely on to arrive at the "north of a billion dollars" figure for an LNG import terminal?

Answered by

Hon Simon Watts

Member for North Shore · National Party · Minister for Energy

Answer

An estimated cost range for the facility services is between $90m - $180m per year. Final costs are still subject to the current procurement process and so will not be publicly released at this time.