What is the current delivery programme (milestones and dates) for (a) completion of geotechnical investigations, (b) route/protected designation steps, (c) procurement, (d) enabling works, and (e) main works for each current tunnel project in Wellington?

Answered Question 5569 (2026)
Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What is the current delivery programme (milestones and dates) for (a) completion of geotechnical investigations, (b) route/protected designation steps, (c) procurement, (d) enabling works, and (e) main works for each current tunnel project in Wellington?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

- Mt Victoria geotechnical investigations completed on 20 February 2026 - Hydrogeological investigations along the proposed route began on 9 February 2026 and will continue through to consent lodgement in mid-2026 - Route protection and designation steps are being progressed through statutory approvals, with intent to seek approval under the Fasttrack Approvals Act 2024, and lodgement of consent applications targeted for mid-2026 - Procurement for a Principal's Technical Advisor (PTA) is underway - NZTA continues to explore options for early works to begin in 2026.