Answered
Question 520 (2026)
- Question published
- Reply lodged
Bookmark
Asked by
Kieran McAnulty
List MP · Labour Party
Question
-
What IT projects, if any, were shelved or curtailed by Kāinga Ora since 1 July 2024 and how much, if anything, was spent on each system in the five years prior to it being shelved or curtailed?
Answered by
Hon Chris Bishop
Member for Hutt South · National Party · Minister of Housing
Answer
Kāinga Ora – Homes and Communities advises me that it discontinued two projects since 1 July 2024. These were a Complaints and Feedback System and an Electronic Timesheet Module. Both these projects were assessed during the Kāinga Ora reshaping process, and it was determined that they did not need to proceed further. There was no project-related spend on these systems.