Further to WPQ 694 (2026), of the 18 projects (119 homes) reforecast from 2025/26 to 2026/27 due to consenting delays, in which regions are those projects located, and what is the average length of delay per project?

Answered Question 5165 (2026)
Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • Further to WPQ 694 (2026), of the 18 projects (119 homes) reforecast from 2025/26 to 2026/27 due to consenting delays, in which regions are those projects located, and what is the average length of delay per project?

Answered by

Hon Tama Potaka

Member for Hamilton West · National Party · Associate Minister of Housing

Answer

Kāinga Ora – Homes and Communities advises me that around 250 homes have been re forecast from 2025/26 to 2026/27 due to extended consenting and engineering approval timeframes. Affected projects are in Auckland, Bay of Plenty, the Eastern North Island, Wellington, and Nelson/Marlborough/West Coast. Delays average 30–60 days.