Further to WPQ 694 (2026), what is the estimated financial impact, if any, of the consenting delays on the 18 reforecast projects, including cost escalation or holding costs?

Answered Question 5163 (2026)
Question published
Reply lodged

Asked by

Kieran McAnulty

List MP · Labour Party

Question

  • Further to WPQ 694 (2026), what is the estimated financial impact, if any, of the consenting delays on the 18 reforecast projects, including cost escalation or holding costs?

Answered by

Hon Tama Potaka

Member for Hamilton West · National Party · Associate Minister of Housing

Answer

Kāinga Ora – Homes and Communities advises me that consenting delays have mainly resulted in deferred rental income and, in some cases, additional redesign work. There are no cost escalation or holding costs. Impacts vary by project and are managed within approved budgets.