What advice, briefings, correspondence or other communication, if any, has the Minister received on the monetary cost of LNG importation into New Zealand?

Answered Question 5133 (2026)
Question published
Reply lodged

Asked by

Steve Abel

List MP · Green Party

Question

  • What advice, briefings, correspondence or other communication, if any, has the Minister received on the monetary cost of LNG importation into New Zealand?

Answered by

Hon Simon Watts

Member for North Shore · National Party · Minister for Energy

Answer

The cost of the facility is estimated to be between $90 and $180 million per year. In addition, LNG is expected to cost between $20-25/GJ to the user.