Of the $42.8 million in technical services recorded in Reply 34451 (2026), what proportion relates to geotechnical investigation data that has been provided to the Northway consortium, and did the consortium pay any amount for that data or receive it at no cost?

Answered Question 39697 (2026)
Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • Of the $42.8 million in technical services recorded in Reply 34451 (2026), what proportion relates to geotechnical investigation data that has been provided to the Northway consortium, and did the consortium pay any amount for that data or receive it at no cost?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

Approximately 40% ($17.5 million) of the $42.8m relates to geotechnical investigation, including all testing and associated professional services. The resulting geotechnical data was provided to all three Respondents during the RFP phase at no cost. This enabled higher quality technical solutions in their final bids. Northway, the successful Respondent, is currently undertaking a further regime of targeted ground investigation work to augment the work carried out by the NZ Transport Agency Waka Kotahi (NZTA). The costs associated with this further work will be borne by Northway.