What is the current total forecast cost of the Cook Strait Ferry Replacement Programme, broken down by vessel construction, Wellington port infrastructure, Picton port infrastructure, programme management and contingency?

Answered Question 39669 (2026)
Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What is the current total forecast cost of the Cook Strait Ferry Replacement Programme, broken down by vessel construction, Wellington port infrastructure, Picton port infrastructure, programme management and contingency?

Answered by

Rt Hon Winston Peters

List MP · NZ First · Minister for Rail

Answer

This was all announced on 17 July 2026. Ship contracts: $596 million All Picton works: $493 million All Wellington Works: $409 million Programme management and total contingencies: $426 million