Question
-
What did the Gateway 3 Investment Decision review of the Northland Corridor Section 1: Warkworth to Te Hana PPP, conducted between 4 and 8 May 2026, record about the value for money of the project following the reduction of the bidder field to a preferred bidder?
Answered by
Hon Chris Bishop
Member for Hutt South · National Party · Minister of Transport
Answer
The review found that NZTA had executed a well-designed competitive procurement process that had maintained commercial tension for as long as possible to ensure value for money and a manageable Crown risk position.