Skip to main content

Does NZTA maintain a central risk register or contingent liability estimate for properties subject to designations for which no construction funding is allocated; if so, what is the current total value recorded; if not, why not?

Answered Question 37318 (2026)
Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • Does NZTA maintain a central risk register or contingent liability estimate for properties subject to designations for which no construction funding is allocated; if so, what is the current total value recorded; if not, why not?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

No. Risks and potential property-related obligations are assessed and managed within individual project governance and business case processes.