- Question published
- Reply lodged
Asked by
Kieran McAnulty
List MP · Labour Party
Question
-
How many, if any, new Kāinga Ora housing complex units were delivered in Fordlands, Rotorua since 1 July 2025 and how many, if any, of those units were tenanted by people from Rotorua?
Answered by
Hon Tama Potaka
Member for Hamilton West · National Party · Associate Minister of Housing
Answer
Kāinga Ora - Homes and Communities advises me that it has not delivered any new housing complex units in Fordlands, Rotorua, between 1 July 2025 and 31 July 2026. In the 2025/2026 Financial Year there were 111 deliveries in the Rotorua TLA, comprising of 70 acquisitions and 41 redevelopments. These deliveries were in the following Census Area Units: Fairy Springs, Glenholme West, Owhata West, Selwyn Heights, Victoria and Western Heights.