Question
-
What weightings were applied to price, quality and risk in evaluating Warkworth to Te Hana proposals, and what score did each shortlisted consortium receive against each criterion?
Answered by
Hon Chris Bishop
Member for Hutt South · National Party · Minister of Transport
Answer
This information cannot be released because it is commercially sensitive. It comprises detailed evaluation methodology, scoring outcomes, and bidder-specific assessments developed as part of a commercially sensitive PPP procurement process. Releasing this information could prejudice the commercial position of the respondents and could undermine NZTA's ability to obtain effective competition and value for money in future competitive PPP procurements by revealing evaluation approaches, comparative strengths and weaknesses, and risk assessments that bidders provided on a confidential basis.