Who will independently verify the Northway consortium's performance against the Warkworth to Te Hana Key Performance Indicators, and at whose cost?
Answered by
Hon Chris Bishop
Member for Hutt South · National Party · Minister of Transport
Answer
I am advised that there is no independent verification of the Northway consortium’s performance against Key Performance Indicators. This assessment is done by NZTA. The Independent Reviewer is jointly engaged and funded by NZTA and Northway SPV. The Independent Reviewer is responsible for verifying that the Works Requirements have been met and that the Works Completion Tests have been achieved.