What earlier Gateway reviews have been conducted on the Warkworth to Te Hana project, on what dates, and what delivery confidence rating did each assign?

Answered Question 34426 (2026)
Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What earlier Gateway reviews have been conducted on the Warkworth to Te Hana project, on what dates, and what delivery confidence rating did each assign?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

I am advised that a Gateway 0/2 Review (Strategic Assessment / Delivery Strategy – Detailed Business Case) was undertaken in February 2025. The delivery confidence rating assigned was Amber/Green.