What costs has the Crown incurred to date for the procurement process for the proposed LNG import facility, broken down by feasibility studies, technical advice, legal advice, and consultancy services?

Answered Question 33946 (2026)
Question published
Reply lodged

Asked by

Megan Woods

Member for Wigram · Labour Party

Question

  • What costs has the Crown incurred to date for the procurement process for the proposed LNG import facility, broken down by feasibility studies, technical advice, legal advice, and consultancy services?

Answered by

Hon Simeon Brown

Member for Pakuranga · National Party · Minister for Energy

Answer

I am advised that the following is a breakdown of costs for the LNG project from fiscal years 2024/25 and 2025/26, through to month end July 2026: • Technical advice: $1.34 million • Legal Advice: $0.43 million • Other consultancy services: $1.23 million • Contractor costs: $0.77 million • Staff costs (direct cost centre only): $0.44 million • Other costs $0.2 million Note staff costs are for FTE within the project cost centre only. Additional input is provided from other parts of MIBE as appropriate, including the Energy Markets team, Legal, Communications, and Ministerial Servicing.