How has a known potential worst case fatality distance of approximately 2km factored into the procurement process for an LNG import facility in Port Taranaki?

Answered Question 33940 (2026)
Question published
Reply lodged

Asked by

Megan Woods

Member for Wigram · Labour Party

Question

  • How has a known potential worst case fatality distance of approximately 2km factored into the procurement process for an LNG import facility in Port Taranaki?

Answered by

Hon Simeon Brown

Member for Pakuranga · National Party · Minister for Energy

Answer

I am advised Health and safety requirements have been incorporated into the procurement process to the extent reasonable for such a process. As the procurement process remains under way I am unable to comment further. Any LNG import facility will be required to meet all applicable health and safety requirements before commencing operations.