Question 33734 (2026)
- Question published
- Reply lodged
Bookmark
Asked by
Tangi Utikere
Member for Palmerston North · Labour Party
Question
-
How much, if any, of the tagged contingency established alongside the $1.7 billion Cook Strait Ferry Replacement Programme funding envelope agreed by Cabinet in March 2025 has been drawn down as at 24 July 2026, and for what purposes?
Answered by
Rt Hon Winston Peters
List MP · NZ First · Minister for Rail
Answer
All of the tagged contingency established in 31 March 2025 has been appropriated and committed to the programme, but none has been drawn.