What contingency, if any, is held within the $373 million Ferry Holdings Limited contribution to Picton marine infrastructure announced on 17 July 2026, and what is its value?

Answered Question 33726 (2026)
Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What contingency, if any, is held within the $373 million Ferry Holdings Limited contribution to Picton marine infrastructure announced on 17 July 2026, and what is its value?

Answered by

Rt Hon Winston Peters

List MP · NZ First · Minister for Rail

Answer

This information is not disclosed for commercial reasons. At a total programme level, approximately 20% of the $1.704 billion Government funding for Ferry Holdings is contingency.