Answered
Question 33680 (2026)
- Question published
- Reply lodged
Bookmark
Asked by
Tangi Utikere
Member for Palmerston North · Labour Party
Question
-
What are the top five risks recorded on the Cook Strait Ferry Replacement Programme risk register as at 24 July 2026, and what is the assessed cost impact of each?
Answered by
Rt Hon Winston Peters
List MP · NZ First · Minister for Rail
Answer
This information is not disclosed. However, standard infrastructure risks apply and approximately 20% contingency is built into the programme which is funded to the relatively high P85 level.