Which Roads of National Significance or other major transport projects, if any, has NZTA surrendered, withdrawn, or allowed to lapse a resource consent or Fast-track approval for since 1 January 2024, and on what dates?

Answered Question 33483 (2026)
Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • Which Roads of National Significance or other major transport projects, if any, has NZTA surrendered, withdrawn, or allowed to lapse a resource consent or Fast-track approval for since 1 January 2024, and on what dates?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

NZTA is currently in the process of withdrawing its resource consent applications for the East West Link project, which were lodged with the Environmental Protection Authority in 2016.