Which Roads of National Significance, if any, hold a resource consent or Fast-track approval that has been granted but not yet given effect, and which of those have a lapse date within the next five years?

Answered Question 33482 (2026)
Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • Which Roads of National Significance, if any, hold a resource consent or Fast-track approval that has been granted but not yet given effect, and which of those have a lapse date within the next five years?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

The Roads of National Significance that have designation alterations, resource consents, and other statutory approvals under the Fast-track Approvals Act are Takitimu Northern Link Stage 2 and Belfast to Pegasus Project. The resource consents granted under the FTAA have lapse dates longer than five years.