Question
-
What extensions to designation lapse dates, if any, has NZTA sought, or does it intend to seek, for Roads of National Significance that have no construction start date in the July 2026 Major Transport Projects Pipeline, and for which projects?
Answered by
Hon Chris Bishop
Member for Hutt South · National Party · Minister of Transport
Answer
NZTA is submitting an application to extend the lapse date for the Mill Road Stage 1 designations. Most other existing designations have been given effect to or have long lapse dates. NZTA will continue to monitor if any lapse dates need to be extended to support future construction start dates.