On what date did he or his office receive the Site Feasibility Report for the Waikato Interim Inpatient Ward dated 14 November 2025, and what did it advise as the expected operational date?

Answered Question 33233 (2026)
Question published
Reply lodged

Asked by

Ayesha Verrall

List MP · Labour Party

Question

  • On what date did he or his office receive the Site Feasibility Report for the Waikato Interim Inpatient Ward dated 14 November 2025, and what did it advise as the expected operational date?

Answered by

Hon Simeon Brown

Member for Pakuranga · National Party · Minister of Health

Answer

I am advised by Health New Zealand that the Site Feasibility report released in OIA HNZ0020362 was generated by Colliers for internal use by Health NZ. This report was an operational report and therefore not shared with me when it was produced. However, my office did receive a copy of the report via a copy of the OIA which was was provided to my office in June 2026. The timeline within the report was an indicative feasibility programme only and did not represent approved project milestones or committed delivery dates.