Question
-
What is the breakdown of costs for the $21.6 million from the Regional Infrastructure Fund allocated for the refurbishment of the two tanks at the Northland fuel import terminal?
Answered by
Hon Shane Jones
List MP · NZ First · Minister for Regional Development
Answer
Channel Infrastructure NZ Limited has completed the refurbishment of two diesel storage tanks and will provide the Crown with storage and associated operational services from June 2026 through to December 2027. The total cost of these services is $1.20 million per month over the 18-month term of the arrangement.