Question 32020 (2026)
- Question published
- Reply lodged
Bookmark
Asked by
Tangi Utikere
Member for Palmerston North · Labour Party
Question
-
Further to reply 30346 (2026), how much of the $415 million allocated to programme management and total contingencies has been drawn down or committed to date, and against which risks or cost pressures was it drawn down or committed, if any?
Answered by
Rt Hon Winston Peters
List MP · NZ First · Minister for Rail
Answer
$28 million has been spent on programme management as of 30 June 2026. This includes direct ship-related costs that sit outside the ship build contract (such as ship brokerage, naval architecture, and interior design), together with Ferry Holding’s operational costs. No contingency allowance has been drawn during this period.