Further to reply 30352 (2026), how much time has been programmed between delivery of each vessel by Guangzhou Shipyard International and its entry into service on the Cook Strait for the delivery voyage, sea trials, Maritime New Zealand certification, crew training, and berth commissioning?

Answered Question 32012 (2026)
Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • Further to reply 30352 (2026), how much time has been programmed between delivery of each vessel by Guangzhou Shipyard International and its entry into service on the Cook Strait for the delivery voyage, sea trials, Maritime New Zealand certification, crew training, and berth commissioning?

Answered by

Rt Hon Winston Peters

List MP · NZ First · Minister for Rail

Answer

This information will be released closer to 2029, but time is allocated for these matters to occur before the first vessel enters service in the first half of 2029.