Further to reply 30345 (2026), what is the current forecast cost at completion for the Cook Strait ferry replacement programme against the budget approved by Cabinet, expressed as a dollar variance, if any?
Answered by
Rt Hon Winston Peters
List MP · NZ First · Minister for Rail
Answer
$1.704 billion is the current taxpayer budget for our contribution to the programme. This gives a variance of $0.000 billion against the budget approved by Cabinet. As a mathematical equation: $1.704 billion minus $1.704 billion equals $0.000 billion.