What targets, if any, have officials set for the participation of local businesses as subcontractors or suppliers on the RiverLink project in Lower Hutt, when were those targets set, and what is performance against them to date?

Answered Question 31911 (2026)
Question published
Reply lodged

Asked by

Ginny Andersen

List MP · Labour Party

Question

  • What targets, if any, have officials set for the participation of local businesses as subcontractors or suppliers on the RiverLink project in Lower Hutt, when were those targets set, and what is performance against them to date?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

I am advised by NZTA that it does not have specific targets for the participation of local businesses. I refer the member to the response to Written Parliamentary Question 31910 (2026) for the framework that has been set.