What is the NZ Transport Agency's total expenditure to date on the East-West Link, if any, broken down by financial year and by project phase?

Answered Question 31840 (2026)
Question published
Reply lodged

Asked by

Tangi Utikere

Member for Palmerston North · Labour Party

Question

  • What is the NZ Transport Agency's total expenditure to date on the East-West Link, if any, broken down by financial year and by project phase?

Answered by

Hon Chris Bishop

Member for Hutt South · National Party · Minister of Transport

Answer

2024/25 Investment Case $3.9 million Pre Implementation $0.166 million 2025/26 (as at 31 May 2026) Investment Case $1.5 million Pre Implementation 2.9 million