Answered
Question 31835 (2026)
- Question published
- Reply lodged
Bookmark
Asked by
Tangi Utikere
Member for Palmerston North · Labour Party
Question
-
What is the NZ Transport Agency's total expenditure to date on Mill Road, if any, broken down by financial year and by project phase?
Answered by
Hon Chris Bishop
Member for Hutt South · National Party · Minister of Transport
Answer
2024/25 Investment Case $4.5 million Pre Implementation $3 million Property $4.5 million 2025/26 (as at 31 May 2026) Investment Case $1.4 million Pre Implementation $24 million Property $43.4 million Please note, figures are inclusive of Mill Road Stage 1, 2 and 3.